Our Services

Get 15% Discount on your First Order

[rank_math_breadcrumb]

Management Question

Description

Part-1: Case study questions

  • Q1. How did the physical environment of the cave affect the rescue plan? Explain in 250 words (3 Marks).
  • Q2. How did the rescue team respond to the risks of the project? Explain in 250 words (3 Marks).
  • Q3. Some have called the rescue a miracle and that luck was the decisive factor. Do you agree? Explain in 150 words (2 Marks)

Part-2: Discussion questions

Please read Chapter 8 Pg-No. 279 & 281 carefully and then give your answers on the basis of your understanding.

  • Q4. Why would people resist a multi project resource scheduling system? (1 Mark) (100 words)
  • Q5. What do you think would have happened if the Washington Forest Service did not assess the impact of resources on their two-year plan? (1 Mark) (100 words).

Notes:❗

  • Need references and use APA style for writing the references
  • All answered must be typed using Times New Roman (size 12, double-spaced) font. No
  • kindly avoid plagiarism💙

reassessed. Cost-time trade-offs can be considered. In some cases priorities
may be changed. See Snapshot from Practice 8.3: U.S. Forest Service
Resource Shortage.
Resource schedules provide the information needed to prepare timephased work package budgets with dates. Once established, they provide a
quick means for a project manager to gauge the impact of unforeseen events
such as turnover, equipment breakdowns, or transfer of project personnel.
Resource schedules also allow project managers to assess how much
flexibility they have over certain resources. This is useful when they receive
requests from other managers to borrow or share resources. Honoring such
requests creates goodwill and an “IOU” that can be cashed in during a time
of need.

SNAPSHOT FROM PRACTICE 8.3
U.S. Forest Service Resource Shortage
A major segment of work in managing U.S. Forest Service (USFS) forests
is selling mature timber to logging companies that harvest the timber under
contract conditions monitored by the service. The proceeds are returned to
the federal government. The budget allocated to each forest depends on
the two-year plan submitted to the U.S. Department of Agriculture.
Olympic Forest headquarters in Olympia, Washington, was developing a two-year
plan as a basis for funding. All of the districts in the forest submitted their timber sale
projects (numbering more than 50) to headquarters, where they were compiled and
aggregated into a project plan for the whole forest. The first computer run was reviewed
by a small group of senior managers to determine if the plan was reasonable and
“doable.” Management was pleased and relieved to note all projects appeared to be
doable in the two-year time frame until a question was raised concerning the computer
printout. “Why are all the columns in these projects labeled ‘RESOURCE’ blank?” The
response from an engineer was “We don’t use that part of the program.”
The discussion that ensued recognized the importance of resources in completing the
two-year plan and ended with a request to “try the program with resources included.” The
new output was startling. The two-year program turned into a three-and-a-half-year plan
because of the shortage of specific labor skills such as road engineer and environmental
impact specialist. Analysis showed that adding only three skilled people would allow the
two-year plan to be completed on time. In addition, further analysis showed hiring only a
few more skilled people, beyond the three, would allow an extra year of projects to also
be compressed into the two-year plan. This would result in additional revenue of more
than $3 million. The Department of Agriculture quickly approved the requested extra
dollars for additional staff to generate the extra revenue.

Darinburt/Getty Images

page 279

8.8 Assigning Project Work
LO 8-7
Identify general guidelines for assigning people to specific tasks.

When making individual assignments, project managers should match, as
best they can, the demands and requirements of specific work with the
qualifications and experience of available participants. In doing so, there is
a natural tendency to assign the best people the most difficult tasks. Project
managers need to be careful not to overdo this. Over time these people may
grow to resent the fact that they are always given the toughest assignments.
At the same time, less experienced participants may resent the fact that they
are never given the opportunity to expand their skill/knowledge base.
Project managers need to balance task performance with the need to
develop the talents of people assigned to the project.
Project managers need to decide not only who does what but also who
works with whom. A number of factors need to be considered in deciding
who should work together. First, to minimize unnecessary tension,
managers should pick people with compatible work habits and personalities
but who complement each other (i.e., one person’s weakness is the other

person’s strength). For example, one person may be brilliant at solving
complex problems but sloppy at documenting his progress. It would be wise
to pair this person with an individual who is good at paying attention to
details. Experience is another factor. Veterans should be teamed up with
new hires—not only so they can share their experience but also to help
socialize the newcomers to the customs and norms of the organization.
Finally, future needs should be considered. If managers have some people
who have never worked together before but who have to later on in the
project, they may be wise to take advantage of opportunities to have these
people work together early on so that they can become familiar with each
other. Finally, see Snapshot from Practice 8.4: Managing Geeks for some
interesting thoughts from the former CEO of Google on how to put together
teams.

SNAPSHOT FROM PRACTICE 8.4
Managing Geeks*
Eric Schmidt, after a successful career at Sun Microsystems, took over
struggling Novell, Inc., and helped turn it around within two years. Four
years later he became the CEO of Google. One of the keys to his success
is his ability to manage the technical wizards who develop the sophisticated
systems, hardware, and software that are the backbone of electronically driven
companies. He uses the term “geek” (and he can, since he is one, with a Ph.D. in
computer science) to describe this group of technologists who rule the cyberworld.
Schmidt has some interesting ideas about assigning geeks to projects. He believes
that putting geeks together in project teams with other geeks creates productive peer
pressure. Geeks care a great deal about how other geeks perceive them. They are good
at judging the quality of technical work and are quick to praise as well as criticize each
other’s work. Some geeks can be unbearably arrogant, but Schmidt claims that having
them work together on projects is the best way to control them—by letting them control
each other.
At the same time, Schmidt argues that too many geeks spoil the soup. By this he
means that when there are too many geeks on a development team, there is a tendency
for intense technical navel gazing. Members lose sight of deadlines, and delays are
inevitable. To combat this tendency, he recommends using geeks only in small groups.
He urges breaking up large projects into smaller, more manageable projects so that
small teams of geeks can be assigned to them. This keeps the project on time and
makes the teams responsible to each other.

*

Russ Mitchel, “How to Manage Geeks,” Fast Company, May 31, 1999, pp. 175–80.
page 280

8.9 Multiproject Resource Schedules
LO 8-8
Identify common problems with multiproject resource scheduling.

For clarity we have discussed key resource allocation issues within the
context of a single project. In reality resource allocation generally occurs in
a multiproject environment where the demands of one project have to be
reconciled with the needs of other projects. Organizations must develop and
manage systems for efficiently allocating and scheduling resources across
several projects with different priorities, resource requirements, sets of
activities, and risks. The system must be dynamic and capable of
accommodating new projects as well as reallocating resources once project
work is completed. While the same resource issues and principles that apply
to a single project also apply to this multiproject environment, application
and solutions are more complex, given the interdependency among projects.
The following are three of the more common problems encountered in
managing multiproject resource schedules. Note that these are macro
manifestations of single-project problems that are now magnified in a
multiproject environment.
1. Overall schedule slippage. Because projects often share resources,
delays in one project can have a ripple effect and delay other projects.
For example, work on one software development project can grind to a
halt because the coders scheduled for the next critical task are late in
completing their work on another development project.
2. Inefficient resource utilization. Because projects have different
schedules and requirements, there are peaks and valleys in overall
resource demands. For example, a firm may have a staff of 10

electricians to meet peak demands when, under normal conditions, only 5
electricians are required.
3. Resource bottlenecks. Delays and schedules are extended as a result of
shortages of critical resources that are required by multiple projects. For
example, at one Lattice Semiconductor facility, project schedules were
delayed because of competition over access to test the equipment
necessary to debug programs. Likewise, several projects at a U.S. forest
area were extended because there was only one silviculturist on the staff.
To deal with these problems, more and more companies are creating project
offices or departments to oversee the scheduling of resources across
multiple projects. One approach to multiple project resource scheduling is
to use a first come–first served rule. A project queue system is created in
which projects currently under way take precedence over new projects.
New project schedules are based on the projected availability of resources.
This queuing tends to lead to more reliable completion estimates and is
preferred on contracted projects that have stiff penalties for being late. The
disadvantages of this deceptively simple approach are that it does not
optimally utilize resources or take into account the priority of the project.
See Snapshot from Practice 8.5: Multiple Project Resource Scheduling.
Many companies utilize more elaborate processes for scheduling
resources to increase the capacity of the organization to initiate projects.
Most of these methods approach the problem by treating individual projects
as part of one big project and adapting the scheduling heuristics previously
introduced to this “mega project.” Project schedulers monitor resource
usage and provide updated schedules based on progress and resource
availability across all projects. One major improvement in project
management software in recent years is the ability to prioritize resource
allocation to specific projects. Projects can be prioritized in ascending order
(e.g., 1, 2, 3, 4, . . .), and these priorities will override scheduling heuristics
so that resources go to the project highest on the priority list. (Note: This
improvement fits perfectly with organizations that use project priority
models similar to those described in Chapter 2.) Centralized project
scheduling also makes it easier to identify resource bottlenecks that stifle
progress on projects. Once bottlenecks have been identified, their impact
page 281
can be documented and used to justify acquiring additional

Purchase answer to see full
attachment

Share This Post

Email
WhatsApp
Facebook
Twitter
LinkedIn
Pinterest
Reddit

Order a Similar Paper and get 15% Discount on your First Order

Related Questions

mgt430 نهايي

Description I want it to be a summary of the three reports, and the presentation should consist of only 5 slides and be simple. Course Name: Internship Student’s Name: Course Code: MGT430 Student’s ID Number: Semester: CRN: Academic Year: 2022-2023 For Instructor’s Use only Instructor’s Name: Students’ Grade: Restricted –

CTA – Project Management

Description Critical Thinking Assignment Module 13: Project Management In this module, you will learn about the behavioral aspects of project management as well as components of the work breakdown structure. Projects are unique undertakings that must support the organization’s strategic plan. Pay attention to the connection between the strategic goals

DB – Waiting Lines

Description Module 14: Waiting Lines in this module, you will learn about the management of waiting lines. The focus will be on the managerial implications of waiting lines to include the cost of providing waiting space and the costs of not providing adequate waiting space to customers. In addition, you

mgt430 فاينل

Description Write the final report accurately and clearly. I will provide you with my information and training information. I do not want to copy or resemble another student.

Dissssss.

Description Module 13: Discussion one file Compare the healthcare systems in Turkey, Egypt, and Jordan. Which system is more like Saudi Arabia? Describe the similarities and the differences. : Module 13: Discussion one file For this discussion, we examine informed consent for different types of consent for treatment and research.

IT354 Project

Description · You must use MySQL for database creation and manipulation. · Select ONE database scenario of your choice. Do not select any scenario which you have studied in the lab/lecture. All your answers should be according to the selected scenario. · Support your answer with a detailed explanation and

MGT430– Presention

Description want a very simple presentation, only important words and a nice slide layout . Five slides are required: 1- The first slide: the cover page. 2- One slide that talks about the organization and myself. 3- Two slides that talk about the tasks, challenges and difficulties. 4- A slide

I have an Internship report need to be written to graduate

Description I trained in ministry of national guard health affairs hospital in the pharmacy section as admin assistant and i need help to write the final report College of Administration and Finance Sciences Form No 4- Internship Report Cover Page Student`s Name: Student`s ID: Trainee Department: Training Organization: Field Instructor

ct

Description Personal Development Plan (110 Points) one file A development plan is a key component of a performance management plan because it guides performance improvement and helps with employee buy-in. Create a short-term development plan (1-2 years) and a long-term development plan (3-5 years) for yourself. In your plan, address

3 ct.

Description The primary objective of this assignment is to explore and implement strategies that improve teamwork in healthcare settings. By fostering effective communication, collaboration, and a positive work environment, healthcare professionals can enhance patient care, safety, and overall outcomes. Create a PowerPoint addressing the following point: 1. Literature Review: Conduct

Did

Description Module 13: Discussion 2 file Compare the healthcare systems in Turkey, Egypt, and Jordan. Which system is more like Saudi Arabia? Describe the similarities and the differences. : Module 13: Discussion 2 file For this discussion, we examine informed consent for different types of consent for treatment and research.

Final presentation for the internship

Description need your support to do a presentation Course Name: Internship Student’s Name: Course Code: MGT430 Student’s ID Number: Semester: CRN: Academic Year: 2022-2023 For Instructor’s Use only Instructor’s Name: Students’ Grade: Restricted – ‫مقيد‬ Level of Marks: Secondary address separator Restricted – ‫مقيد‬ Restricted – ‫مقيد‬ Secondary address Restricted

Reply 1 AT to discussion (Waiting Lines)

Description Q – Please read the discussion Attached and prepare a Reply to this discussion post with comments that further and advance the discussion topic. The reply needs to be substantial and constructive in nature. it should add to the content of the post and evaluate/analyze that post Discussion Please

Reply 2 AA to discussion (Waiting Lines)

Description Q – Please read the discussion Attached and prepare a Reply to this discussion post with comments that further and advance the discussion topic. The reply needs to be substantial and constructive in nature. it should add to the content of the post and evaluate/analyze that post Discussion Please

499 training

Description Training presen z Public Health Internship ▪ My name: Ibrahim Mohammed Ali Hadaddi ▪ Instructor Name: Dr. Olfat z Abdulgafoor Gushgari ▪ ID: 170190568 ▪ CRN:24545 ▪ PHC499 z Organization I had a chance to perform my internship at vector control center in Jazan city. I had performed the

Reply to Waiting Lines Discussion 2

Description Reply to Waiting Lines Discussion 2 Q – Please read the discussion below and prepare a Reply to this discussion post with comments that further and advance the discussion topic. Please provide the references you used. Ensure zero plagiarism. Word limit: 130 words Discussion Waiting Lines Businesses utilize waiting

dis 1 with reply

Description Adopted by all United Nations Member States in 2015, the Sustainable Development Goals (SDG)s provide a shared proposal for peace and prosperity for individuals and the planet, now and into the future. The 17 SDGs are an urgent call for action for a global partnership among all developed and